Existing Buildings Energy Efficiency Action Plan Committee 2017 Implementation Plan

Minimize

Committee Description/Mission:

The mission of this committee is to provide input into the California Energy Commission (CEC) Existing Buildings Energy Efficiency Action Plan (EBEE-AP) as desired and necessary. WHPA members and industry will work collaboratively with the California Public Utility Commission (CPUC) and Investor Owned Utilities (IOUs) to help reach consensus on the energy savings aspects of HVAC installation and maintenance.

PDF of Implementation Plan

Goal #1: Launch 2017 EBEE Committee
Milestone Owner Deliverable Due Date Dependencies
  1. Hold 2017 Committee Kick-Off Meeting
Chairs and Committee Members Agenda and Meeting Minutes February 2, 2017
  • Availability of Chairs and Members
  1. EC-approved new Co-Chair to replace Liz Yager
WHPA Staff, Chairs, and EC Approved new Co-Chair February 15, 2017
  • Availability of WHPA Staff Chairs and EC
  1. Review and Update Committee Roster
WHPA Staff and Chairs 2017 Committee Roster February 28, 2017
  • Availability of WHPA Staff and Chairs
  • Willingness of members to participate in Committee
  1. Determine CEC Existing Buildings Unit’s Suggested Foci
WHPA Staff and Chairs Discussion March 31, 2017
  • Availability of Chairs and CEC Staff
  1. Develop Draft Goals
WHPA Staff and Chairs Draft Goals April 15, 2017
  • Availability of WHPA Staff and Chairs
  1. Develop Draft Implementation Plan
WHPA Staff and Chairs Draft Implementation Plan April 30, 2016
  • Availability of WHPA Staff and Chairs
  1. Finalize Goals and Implementation Plan
WHPA Staff and Chairs Final SMART Goals and Implementation Plan May 31, 2017
  • Availability of Chairs and Committee Members
Goal #2: Develop a stakeholder community outreach and education informational resource to improve understanding of key elements referenced in EBEE-AP Strategy 1.9 and its Sub-Strategies (1.9.1 thru 1.9.6) through the HVAC lens.
Milestone Owner Deliverable Due Date Dependencies
  1. Identify Subject Matter Experts (SME) that can inform WHPA EBEE members on key topics related to EBEE-AP Strategy 1.9 and its Sub-Strategies
Chairs and Committee Members List of Identified Relevant SME Speakers Ongoing thru August 2017
  • Availability of Chairs, Members, and SMEs
  1. Coordinate and Host SME informative Presentations and Q&A Sessions relevant to Strategy 1.9, (including 2a thru 2d below)
Chairs and WHPA Staff
  • Presentation Materials
  • Meeting Notes
  • Links posted to WHPA website
Ongoing thru August 2017
  • Availability of Chairs, Members, WHPA Staff, and SMEs
    1. CAEECC Overview Presented and Discussed
SME, Chairs and WHPA Staff
  • CAEECC Overview Slides and Related Discussion Notes
April 6, 2017
  • Availability of Chairs, Members, WHPA Staff, and SMEs
    1. SME IOU Business Plans Presented and Discussed
SME, Chairs and WHPA Staff
  • IOU Business Plan Slides and Related Discussion Notes
April 6, 2017
  • Availability of Chairs, Members, WHPA Staff, and SMEs
    1. SME Cal TF Overview Presented and Discussed
SME, Chairs and WHPA Staff
  • Cal TF Slides and Related Discussion Notes
April 20, 2017
  • Availability of Chairs, Members, WHPA Staff, and SMEs
    1. SB350 Responsible Contractor Policy Study Presented and Discussed
SME, Chairs and WHPA Staff
  • SB 350 Responsible Contractor Policy Study Slides and Related Discussion Notes
May 4, 2017
  • Availability of Chairs, Members, WHPA Staff, and SMEs
  1. Develop, vet and approve a Stakeholder Engagement Feedback Loop Process for how to approach work on the EBEE-AP 1.9 Sub-Strategies.
Chairs, Committee Members EBEE Committee approved Stakeholder Engagement Feedback Loop Process May 18, 2017
  • Availability of Chairs, Members, WHPA Staff, and SMEs
  1. Implement Stakeholder Engagement Feedback Loop Process for EBEE-AP 1.9 Sub-Strategy development
Chairs, Committee Members, SMEs Discussion Notes Ongoing June 2017 thru August 2017
  • Availability of Chairs, Members, and SMEs
  1. Capture identified stakeholder comments, concerns, highlighted potential solutions, and presentation material links in the Draft Work Product III document
Chairs and WHPA Staff Draft Work Product III: Addressing California EBEE-AP Strategy 1.9 Through the HVAC Lens - Stakeholder Community Outreach and Education September 21, 2017
  • Availability of Chairs and WHPA Staff
  1. Approve Work Product III for escalation to the EC
Committee Chairs and EWG EBEE Approved Final Draft Work Product III October 19, 2017
  • Availability of Chairs and Members
  1. Present Work Product III findings to the EC
Committee Chairs, EC, and WHPA Staff EC Approved Work Product III November 15, 2017
  • Availability of Chairs, EC, and WHPA Staff
  • Time on November EC Agenda
  1. Approved Work Product III shared with CEC and relevant stakeholders, plus posted to the WHPA website
WHPA Staff Website Updated and Notifications Emailed to Stakeholders December 31, 2017
  • Availability of WHPA Staff
Copyright 2018 by Western HVAC Performance Alliance